Learn about Portfolios, a new feature designed to help users track and manage multiple plans in Planner.
Updated Dec 02, 2024
Version 1.0Hi - super excited for the launch of Portfolios! Wanted to understand what 'milestones' refers to in this view? Is this a 'teams' feature only? I don't have teams in my Enterprise, so want to understand if this is something I can use or not. Thank you! Meet_Sanghvi
Milestones are a "special" task - 0 days duration. When you select "all milestones", the roadmap view pulls in just your milestones from the underlying plan (from my use, that's what I am seeing). I pull in milestones and all top level tasks and it produces a nice timeline view.
thank you so much for that insight! Worked exactly as you described. 😀