Tracking when a due date is changed

Copper Contributor

Hello,

 

I have a management issue with MS PLaner. Team member are changing the due date and I don't find a way to know what was the old due date and / or who changed the dead line.  I think it could be a good way to integrate / follow the modification of due date in the comment for each task.

Do you know if this feature already exhist ? How are you dealing with this kinf of issue ?

 

Thank you !

2 Replies

@GuillaumeW 

 

Yeah, it would be great see see this as a track history, but doesn't exist as of today! The thing with planner is that everyone can do a bit of everything making it hard to use this tool for any type of real control as a manager or owner! The purpose is really, "WE need to have an overview of our tasks as a team" 

 

I'll suggest going to planner uservoice and see if there's any similar requests or just create your own!

 

https://planner.uservoice.com/forums/330525-microsoft-planner-feedback-forum?query=track

 

Adam

@adam deltinger  thank you for your quick answer. I will have a look at your link.