Report for tasks moved from one Sprint to another
Good Day I need help. How do I run a report to see tasks that were moved from one Sprint to another. I am currently on Sprint 4, I want to see tasks that were moved from Sprint 2 to Sprint 3 to Spr...
trishmcdonough
Copper Contributor
Are you just moving the Task and leaving the parent work item in the original sprint?
If so, you could do a 'Work Items and Direct Links' query to return tasks where the parent has a different iteration path.
If so, you could do a 'Work Items and Direct Links' query to return tasks where the parent has a different iteration path.
Prabhatnath
Sep 06, 2023Copper Contributor
Hi, trishmcdonough can you help explain a little about this approach from Power BI or any other way? Sindi_Jacobsson are you able to get this working? I am also looking for an approach to identify work items that have been moved from the previous sprint to the current.
Thanks,
Prabhat