2 TopicsHow to make finish date not inclusive date in Microsoft project?
How to change the finish date not to be inclusive? for example, if the duration date is 1 day, the finish date should be the same as the start date. and if 2 days, if start date on Monday, finish date to be on Tuesday, not Wednesday. As this is what happens to me? I want it to be in a sequence and not inclusive, t1 5/7 -> 5/7 t2 6/7 -> 7/7 t3 8/7 -> 8/7 like that for example:1KViews0likes0Comments