I have a project server 2019
Suddenly when I add any tasks or projects don't reflect in capacity planning although they appear all in resource assignments.
I checked all the following:
- the box of “include proposed bookings” is checked
- I'm using enterprise resources, not local
- the project publish correctly with no error messages in the queue
#SharePoint
#projectServer
Oct 22 2020 02:38 AM
@sherry_gamal It's a known issues that Microsoft says they aren't planning to fix! At least that was the feedback I got from the product team about 10 months ago! I do hope that will change. Its an issue in Project Online too...