04-23-2020 05:15 AM - edited 04-23-2020 05:35 AM
Hello everyone,
I'm having trouble to figure out where a project resides that I create via Project Home -> New blank project ("Project for the web").
Is there a way to see or move such project to the Project Online PWA Site? Or do I either do one or the other?
Thank you!
04-23-2020 05:53 AM
SolutionHi @HelgeDV
Project for the web data just like Roadmaps data resides in the Common Data Service default environment.
Project Online data resides in the respective SharePoint site.
Moving data from one to the other is a manual process (do one or the other) that can be automated to a certain degree using Power Automate or other integration tools.