SOLVED

What's the best way to graphically view resource utilisation in Project?

Copper Contributor

Long time P6 user, looking for something similar to this in MSP...

 

dc_27_0-1662880674508.png

 

A list of all my resources, against their utilisation in graphical (not tablature) form

 

I've tried Resource Graph, but that seems like you have to scroll around to see the resources - i cant select more than one resource to see cumulative

 

dc_27_1-1662880858958.png

 

Any suggestions appreciated

David

5 Replies
best response confirmed by dc_27 (Copper Contributor)
Solution

@dc_27 

Yes you can see multiple resources on the Resource Graph. First you have to set up the Resource Graph Bar Styles to be active for "selected resources" as shown here.

2022-09-11_07-00-17.png

 

Then on either the Resource Sheet or Resource Usage, select a single or group of resources. In my sample file, it looks like this when two team resources are selected.

2022-09-11_07-09-37.png

But, just for reference, Project doesn't have a lot of flexibility for graphing resources. You can try the Resource Graph or one of the Reports but you may find it is best to export Project data to Excel and graph it there.

John

Thanks again.

And thanks for the note on exporting to Excel - suspect they would anticipate use of Power BI for more flexible reporting, or indeed Excel
dc_27,
You're welcome and thanks for the feedback.

I'm a VBA guy so I use that for communicating between Project and Excel.
John
Just on the resource graph again - is there anything i need to do / not do to get a graph for multiple resources?

When i select more than one, the graph is only shown for the initially selected resource
dc_27,
Look carefully at the Bar Styles window shown in my previous response. On the right side you set up bar styles for a single resource. On the left side you set up bar styles for multiple resources (i.e. selected or filtered). If you only have bar styles for a single resource it will show the first resource in a multiple selection. To only see multiple resources, turn off bar styles for a single resource.
John
1 best response

Accepted Solutions
best response confirmed by dc_27 (Copper Contributor)
Solution

@dc_27 

Yes you can see multiple resources on the Resource Graph. First you have to set up the Resource Graph Bar Styles to be active for "selected resources" as shown here.

2022-09-11_07-00-17.png

 

Then on either the Resource Sheet or Resource Usage, select a single or group of resources. In my sample file, it looks like this when two team resources are selected.

2022-09-11_07-09-37.png

But, just for reference, Project doesn't have a lot of flexibility for graphing resources. You can try the Resource Graph or one of the Reports but you may find it is best to export Project data to Excel and graph it there.

John

View solution in original post