I haven't figured out what is Filtered resource in the bar style menu of the resource chart. As opposite to "Resource".
Sep 07 2022 12:01 PM
SolutionYann-78,
The Resource Graph can be set up to show either a single resource or multiple resources. The "filtered resource" is used to set the bar type when multiple resources are selected. For example, in the following screen shot two resource groups are selected. The Resource Graph shows the combined percent work allocated for the two resources.
Hope this helps.
John
Sep 07 2022 12:01 PM
SolutionYann-78,
The Resource Graph can be set up to show either a single resource or multiple resources. The "filtered resource" is used to set the bar type when multiple resources are selected. For example, in the following screen shot two resource groups are selected. The Resource Graph shows the combined percent work allocated for the two resources.