Apr 22 2021 08:36 AM
Description
Within MS Project you can set the calendar options (File – Options – Planning – Calendar Options).
This can then be done for specific projects or for all new projects.
I change the settings for working time to: 9 hours and working days to: 31 for all new projects (The store is open on all days of the week)
In my new project this will be taken over. But what is the effect??
The calendar-settings for that new project will not be adjusted!
So what is the effect in my new project if the calendar isn't changed??
I still have a working day of 8 hours and a working month of 20 days in the ProjectCalendar.
Question
What is the effect of the custom settings by changing the Back-stage stage if the standard calendar isn't changed?
Apr 22 2021 11:21 AM
Apr 22 2021 12:41 PM
Apr 23 2021 01:52 AM
Apr 23 2021 08:43 AM