Hi,
For Timesheet In Project Server 2019 on prem,
For Project Level Reporting or Top Level Reporting
I have 2 questions :
1 - Unless I assign the resource against task, he is not getting timesheet generated for him
For Top Level reporting- I thought resource assignment is not needed against task
2.1- What is the benefit of this piece of functionality ? any scenarios if someone can share ?
2.2 - Where can I see the summary of report generated by this approcah...
Appreciate any suggestions...