Web Project - Select a default view when opening the resource page

Copper Contributor

Hello,

The resource site on PWA 2013 remembers the last view that I had, however it is requested to always open up a default view and not the last selected one.

 

Can anyone help with this?

 

Thank you

1 Reply
best response confirmed by Dale_HowardMVP (MVP)
Solution

Hello @shiromeri ,

The PWA views will always open the last view the user went to. There are default system views that will be used for a new user who has not accessed the page / view before but you are not able to change what view is classed the default system view.

Paul

1 best response

Accepted Solutions
best response confirmed by Dale_HowardMVP (MVP)
Solution

Hello @shiromeri ,

The PWA views will always open the last view the user went to. There are default system views that will be used for a new user who has not accessed the page / view before but you are not able to change what view is classed the default system view.

Paul

View solution in original post