Mar 01 2022 11:09 AM
Can we see a Project that is in project.microsoft.com in MS Teams, Dynamics and project online? Can we change where we see it?
If I created a project in MS Teams project, can I see it Online as well?
Thanks
Mar 01 2022 03:50 PM
SolutionHello @Nancy DEMERS ,
Project for the web projects can be view at project.microsoft.com, in MS Teams and in the Power Apps Project app (or custom App). Out of the box these projects cannot be seen in Project Online - Project Web App.
Projects created in the "Project" app for MS Teams are Project for the web projects - out of the box these cannot be seen in Project Online - Project Web App.
I hope that helps.
Paul
Mar 01 2022 03:50 PM
SolutionHello @Nancy DEMERS ,
Project for the web projects can be view at project.microsoft.com, in MS Teams and in the Power Apps Project app (or custom App). Out of the box these projects cannot be seen in Project Online - Project Web App.
Projects created in the "Project" app for MS Teams are Project for the web projects - out of the box these cannot be seen in Project Online - Project Web App.
I hope that helps.
Paul