Nov 28 2022 08:56 AM - edited Nov 28 2022 08:59 AM
Is it possible to use MS Project as a Resource Planner/Tracker?
If so, how would I set this up in Project?
Which views would be best to track this information?
I cannot figure out how to format the Hours, Duration, Start/End time as I want to see the number of hours each Resource is assigned to a task/project on a weekly basis.
If a new task needs to be assigned, I want to see how many hours each Resource is working (per week per task), so I can make properly reassign tasks.
Project A: Task 1, Task 2
Project B: Task 3, Task 4
Resource A
Resource B
Resource C
Resource A is assigned to Task 1 (20 hrs/wk) & Task 2 (20 hrs/wk)
Resource B is assigned to Task 3 (10 hrs/wk) & Task 4 (30 hrs/wk)
Resource C is assigned to Task 1 (10 hrs/wk)
I want to see all Resources assigned to each Task & each project.
I want to see all Tasks listed under a Project.
I want to see all Tasks assigned to a Resource.
Nov 28 2022 09:08 AM
Nov 28 2022 09:17 AM
What version of Project are you using -- Desktop Project Standard
Is each "project" a separate file or simply different summary groups in a single file?-- Different summary groups in a single file
Attached are screenshots of 3 different views I think I want to use. But, I am not sure how to properly format the views/tasks to show the number of weekly hours assigned to a task versus total hours assigned throughout the year.
Nov 28 2022 12:07 PM
SolutionNov 29 2022 08:13 AM
I also note that your task durations are all 5 days yet the resource hours do not add up to what is normally a full workweek (i.e. 40h). If your tasks are supposed to be for a fixed time span then I suggest you set the tasks as Fixed Duration and adjust resource hours as desired to occur anytime during that span.
Since these are ongoing tasks that the Resource works on throughout the entire year, I changed the start date to 9/1/22 to 8/31/23 since those are the start and end dates of the fiscal year for my company. I am assuming that would be the correct way to set the duration, start, and finish values. Correct?
As far as setting up the Task or Resource Usage views for weekly and yearly resource work loads, set the timescale to show weeks for weekly spread and a separate view with the timescale set to show years for yearly hours.
Alternately, you can set the timescale to show weeks and then add the Cumulative Work field in the Details. You'll have to do a little math with the cumulative values see the difference year to year, but it will all be in one view.
Instead of depending on the Columns to display the number of weekly hours per resource, I should use the Timeline to view that information. Correct?
It sounds like the best views for my needs will be the Resource Usage, Task Usage, and Task Sheet. Correct?
Thank You! This has been super helpful.
Nov 29 2022 10:14 AM
Nov 30 2022 09:57 AM
Thank you, this has been extremely helpful. My file is now setup & formatted with the information that I need to show. I appreciate the time you have taken to help.
Nov 30 2022 10:44 AM
You're welcome and thanks for the feedback. If I answered your questions please consider marking one of my responses as the answer.
John
Nov 28 2022 12:07 PM
Solution