Using enterprise custom fields

Copper Contributor

Hello

I created an enterprise resource field called Limit_hours as shown below where I could enter max hours a resource could work.

Lakshmisv_0-1690544500737.png

Lakshmisv_1-1690544567662.png

When I try to edit the resource in pwa, I am able to add a value which is saved

Lakshmisv_2-1690544841047.png

 

But I am not able to i. Add this field as a column in resource centre.

ii. Add this field as a column in resource sheet in project professional.

 

Please advise on why this is happening.

Thanks

 

 

 

2 Replies
best response confirmed by Lakshmisv (Copper Contributor)
Solution
Lakshmisv --

Delete this field and recreate it as a custom Number field and let us know the result.

@Dale HowardThanks for your reply.

Surprisingly both things work today with no changes made from my side.

Looks like it needed a time gap to sync with the server!

1 best response

Accepted Solutions
best response confirmed by Lakshmisv (Copper Contributor)
Solution
Lakshmisv --

Delete this field and recreate it as a custom Number field and let us know the result.