Jun 02 2022 05:49 PM
Hi,
I have created a schedule and created the 1st baseline ("Baseline Finish" column) based on an overall program plan. The task tracking has begun and Finish column now shows the forecasted finish date.
Now I've been told that a lot of dates in the original program plan were incorrect and have been given a new set of "corrected initial baseline dates". Therefore I need to update the Baseline Finish column.
How do I do that ?
Even if I clear the existing baseline and set a new baseline the dates in Finish column would become the new baseline.
So how do I modify / edit dates in Baseline Finish Col ?
For Eg.
In the attached image, Corrected Baseline Date is a text col, whose dates need to come in Baseline Finish Column. How do I change the dates in baseline finish ?
Any thoughts ?
Jun 02 2022 07:01 PM
SolutionJun 05 2022 03:43 PM
Jun 05 2022 05:11 PM
Jun 02 2022 07:01 PM
Solution