Uninstall Project for the Web steps

Brass Contributor

We have been speaking to a number of our customers about trying out Project for the Web, and being not unreasonable people, they want to know how they will remove P4W from their Default CDS environment should they decide not to proceed.

 

What is the correct sequence for uninstalling the managed solutions that P4W installs?

Is there another way to remove P4W from the Default environment?

 

1 Reply
best response confirmed by Donal McCarthy (Brass Contributor)
Solution

Hi @Donal McCarthy 

Below article has information on how to remove Project for the Web from Office 365. Hope this helps.

 

https://docs.microsoft.com/en-us/project-for-the-web/remove-roadmap-from-office-365 

 

To remove Project for the web:

  1. In the Microsoft 365 admin center, under Admin centers, click Dynamics 365.
  2. In the Dynamics 365 Administration Center, select the default instance, and then click Open.
  3. On the PowerApps page, click the Settings icon, and then click Advanced Settings.
  4. On the Settings menu, under Customization, click Solutions.
  5. Select the msdyn_ProjectServiceCore solution, and then click Delete.
  6. Select the MicrosoftDynamicsScheduling solution, and then click Delete.
  7. Select the msdynce_SchedulingPatch solution, and then click Delete.
  8. Select the msdynce_Scheduling solution, and then click Delete.
  9. . Select any solutions with a naming format of msdyn_ProjectServiceCore_Patch_(number), (for example, msdyn_ProjectServiceCore_Patch_1 or msdyn_ProjectServiceCore_Patch_2), and then click Delete.

Kiran Khanvilkar

1 best response

Accepted Solutions
best response confirmed by Donal McCarthy (Brass Contributor)
Solution

Hi @Donal McCarthy 

Below article has information on how to remove Project for the Web from Office 365. Hope this helps.

 

https://docs.microsoft.com/en-us/project-for-the-web/remove-roadmap-from-office-365 

 

To remove Project for the web:

  1. In the Microsoft 365 admin center, under Admin centers, click Dynamics 365.
  2. In the Dynamics 365 Administration Center, select the default instance, and then click Open.
  3. On the PowerApps page, click the Settings icon, and then click Advanced Settings.
  4. On the Settings menu, under Customization, click Solutions.
  5. Select the msdyn_ProjectServiceCore solution, and then click Delete.
  6. Select the MicrosoftDynamicsScheduling solution, and then click Delete.
  7. Select the msdynce_SchedulingPatch solution, and then click Delete.
  8. Select the msdynce_Scheduling solution, and then click Delete.
  9. . Select any solutions with a naming format of msdyn_ProjectServiceCore_Patch_(number), (for example, msdyn_ProjectServiceCore_Patch_1 or msdyn_ProjectServiceCore_Patch_2), and then click Delete.

Kiran Khanvilkar