Unable to open a project in Project Pro : project seems to be locked for status report update ?

Occasional Contributor

Hi all, 

 

I do not get to open a project with Project Professionnal (desktop) for update, the error message saying : 

"Unable to open the project in R/W mode, because it is locked for the Status Report update on the server". 

(Sorry for the FR translation) 

 

Did anyone already encounter this ?

 

Thank you, 

Laurent

1 Reply
best response confirmed by Dale Howard (MVP)
Solution
Hello,
After reading a post on a blog, I cleaned the MS Project cache (AppData\Roaming\Microsoft\MS Project\Cache) and it works now.

Thank's for helping.

Laurent.