Tracking Ghant -tracking view. % complete planned column

Copper Contributor

Pls assist I need to add a column to show the % that was planned (ie Baseline % ??on the tracking ghant in tracking Form.  (it only % complete on current updating

1 Reply
JeanineB007,
Okay, but first you will have to define exactly what you mean by "planned % complete". Percent complete is the ratio or actual duration to duration and those are the fields used by Project to calculate the % Complete value.

Some options are: Actual Duration compared to Baseline Duration, Baseline Start to Status date compared to Baseline Duration, or something else.

And what exactly is the "tracking Form"?

John