Sep 15 2022 12:55 AM
Sep 15 2022 12:35 PM
Sep 15 2022 10:26 PM
I don't have an option to upload images. So please find the below table which explains my requirements. It's a remote task and not on-site work. Work calendars are the same.
I need a similar setup, I don't want to keep both the people in the same column then it will be difficult to track the % completion by each region.
Both regions need to do the same task.
Task Name | Duration | Deadline | Resource 1 | Resource 1 completion % | Resource 2 | Resource 2 Completion % |
Template completion | 4D | 30/9 | David | 20 | Peter | 30 |
Sep 16 2022 08:20 AM - edited Sep 16 2022 10:45 AM
You should be able to attach an image using the "insert photo" icon on the message toolbar. Or, some users attach a link to a DropBox or other sharing apps. As far as capturing an image, you can use the Windows Snipping tool. I used that for the following screen shot.
Based on what you posted this is how you might set up the tasking. You didn't say whether the Singapore and Africa tasks are performed concurrently or at different times. I assumed concurrent so assigned both resources at 50% to avoid overallocation.
This shows completion by resource (Resource Usage view)
And this shows completion by task (Task Usage view). Sorry, I couldn't post a direct screen shot (forum edit function crashed on me) but you should be able to open the linked PNG file shown.
John