SOLVED

Total total peak units per task

Copper Contributor

Hi Everyone,

 

I´ve searched everywhere and i can't still figure out how to show the total peak unit per tasks and/or summary task?MS project.jpg

 

For example, if I've got a task with 2 resources I would like to see that task showing 2 units in the same row as the task name.

 

See attached image for better understanding.

 

Thanks

3 Replies
best response confirmed by Dale_HowardMVP (MVP)
Solution
Migeul Marques,
Sorry but the only way I can see to get what you want is to export Project data to Excel and then create the total values in a custom report. There is no way to do it directly in Project.
John
Thanks for your reply. Usually, i do that way buti was trying to do it more efficiently/faster way.

Thanks, cheers
Miguel Marques,
You're welcome and thanks for the quick feedback. I've done something similar many times with VBA.
John
1 best response

Accepted Solutions
best response confirmed by Dale_HowardMVP (MVP)
Solution
Migeul Marques,
Sorry but the only way I can see to get what you want is to export Project data to Excel and then create the total values in a custom report. There is no way to do it directly in Project.
John

View solution in original post