Nov 30 2023 10:55 AM
The picture below shows the progress of a project. Going from the bottom to the top, the light blue lines indicates the activities, the yellow lines indicates summary tasks, and the blue line indicates a summary task that contains everything else. The names are based on the WBS Code of each element.
All activities have been updated by their % complete. As we see, the "greyed" part of each line is extremely close to the "Today" line in all elements, but in the "1.5.2" bar, it suggests that there is a full month delay.
Any help on this?
Nov 30 2023 11:03 AM
Nov 30 2023 01:16 PM
Hi @Dale_HowardMVP and thank you for your reply. Here is your request, color coded to match the Timeline View
Dec 01 2023 05:46 AM