Timeline showing 1 year later

Copper Contributor

Hi all, I have created a program tracker Gannt chart with a timeline running along the top. I have set the start dates and finish dates as 01/04/22 - 31/03/25. When I look at the timeline, it has the "today" bar at the right day and month, but the timeline is a year out and is at 2023. Anyone have any clue how to change it? I have attached a pic...

 

Dive1082_0-1655824769589.jpeg

 

1 Reply
best response confirmed by Dale Howard (MVP)
Solution
Its ok, I worked it out. For anyone else with a similar query, you click "file">"options">"Schedule"check the box that says "Use starting year for FY numbering" then click ok