Oct 28 2021 09:24 AM
Hello,
In my Project pro or in my PWA instance I am the only user, so I don't understand how this file can be extracted by somebody else. I'm not able to archive this project.
What can I do to archive this project ?
Thanks for your help
Oct 28 2021 11:03 AM
SolutionHello @Robert0842 ,
You possibly have the project checked out for editing in PWA directly? Access this page {PWAURL}/_layouts/15/pwa/Admin/ForceCheckin.aspx and see if the project is listed there and checked out to you. If it is, check it back in and the problem should be sorted.
Paul
Oct 29 2021 08:35 AM