The Actual Work for Material Resources in 'Resource Work Summary report' is calculated incorrectly,y

Occasional Visitor
I am trying to run the visual report 'Resource Work Summary report' [Monthly] for a project with resources [Materials and Manpower assigned]. The dropbox link for the similar sample file is https://www.dropbox.com/s/4diq31u7s3ouell/Resource%20Usage%20project.mpp?dl=0
 
 
In the report, the actual work for material resources is some arbitrary value [because I am unable to decode the logic in which these numbers are being generated]. The link for the report is below
 
Ideally, in the report, the actual work for Concrete should be 130 cu.m and Rebar 60 tons.
 
 help me in resolving this issue. I have tried in other users systems too, but the issue still persists. 
 
 
 