Jun 13 2022 08:00 PM
Hi again,
I have a project that's published to the PWA and have connected a SharePoint site to the project. However on the SharePoint site when I click on tasks it shows nothing, only a message saying, "This project can only be edited through Project Web App".
Changed to Gantt Chart view to see if it would make a difference -
However if I click "Open with Project", it opens my Project Professional 3 desktop application populated with the correct tasks.
Jun 14 2022 01:01 AM
SolutionHello @BlissL ,
If you want to see the Tasks synchronised to the Project site from PWA, you need to see the option on the Enterprise Project Type:
Next time you publish the project/s the tasks for that project that was published will sync to the Project Site.
Paul
Jun 14 2022 01:01 AM
SolutionHello @BlissL ,
If you want to see the Tasks synchronised to the Project site from PWA, you need to see the option on the Enterprise Project Type:
Next time you publish the project/s the tasks for that project that was published will sync to the Project Site.
Paul