Tasks assignments notifications address - Can it be changed?

Brass Contributor

Is there a way to change the email address (no-reply@sharepointonline.com) where the tasks assignment notifications come from for Project Online?

 

Thanks in advance!

1 Reply

Hello @CG-1717 ,

Unfortunately the from address is not configurable - probably to prevent the emails being blocked / seen as SPAM etc. There are a few feature requests to implement this so it might be worth voting on those:

https://sharepoint.uservoice.com/forums/330318-sharepoint-administration/suggestions/35684299-allow-...

https://office365.uservoice.com/forums/264636-general/suggestions/18692557-please-allow-us-to-change...

As Project Online is a SharePoint Online based application, the same would apply to Project too.

Paul