SOLVED

Sync Dynamics 365 PSA with MS Project Online

Copper Contributor

Hello,

 

We need to have two-way sync between MS Project Online and Dynamics 365 Project Service Automation using Out of Box implementation.

 

If OOTB is not possible then custom development way is also work.

 

Any kind of help will be highly appreciated.

 

Thank You

1 Reply
best response confirmed by Dale Howard (MVP)
Solution

Hello @Inkey_Solutions ,

There is no out of the box sync between these two products. For PSA you used to be able to use MS Project desktop but PSA has now evolved into Project Operation. https://docs.microsoft.com/en-us/dynamics365/project-operations/psa/add-plan-work-microsoft-project 

If you want to sync PSA with Project Online, you might need to look for a 3rd party solution (I don't know of any) or build something.

Paul

1 best response

Accepted Solutions
best response confirmed by Dale Howard (MVP)
Solution

Hello @Inkey_Solutions ,

There is no out of the box sync between these two products. For PSA you used to be able to use MS Project desktop but PSA has now evolved into Project Operation. https://docs.microsoft.com/en-us/dynamics365/project-operations/psa/add-plan-work-microsoft-project 

If you want to sync PSA with Project Online, you might need to look for a 3rd party solution (I don't know of any) or build something.

Paul