Summary tasks calculate total of filtered items only

New Contributor

how to make project calculate the cost for only filtered items ?

3 Replies

Mate89,
Apply the filter and then group the tasks using Project's Grouping feature.

 

For example, in the following simple plan the Flag1 field is the criteria for filtering.

2022-12-25_09-55-11.png

Now the filter is applied and then grouped on the Flag1 field.

2022-12-25_09-56-10.png


John

is there an easier way ?

Matef89,
Short answer, no.

You could use a custom Cost field that is only populated for those tasks that are selected by the filter and then use the sum rollup for the summary task. Or, a simple macro could be used to sum up only the filtered tasks and write the cost into a separate Cost field.
John