Summary task doesn't consider sub task dates

%3CLINGO-SUB%20id%3D%22lingo-sub-839971%22%20slang%3D%22en-US%22%3ESummary%20task%20doesn't%20consider%20sub%20task%20dates%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-839971%22%20slang%3D%22en-US%22%3E%3CP%3EHi%20folks%20-%20I%20am%20new%20to%20MS%20project%20and%20am%20struggling%20with%20the%20metadata%20on%20summary%20tasks.%20You%20can%20see%20in%20this%20image%20I%20have%20an%20'Initiate%20Project'%20summary%20task%20which%20consists%20of%20several%20sub-tasks.%20When%20I%20mark%20one%20of%20the%20subtasks%20complete%2C%20Project%20marks%20the%20summary%20task%20complete%20too.%20Even%20though%20all%20of%20the%20other%20subtasks%20are%20still%20incomplete.%20The%20summary%20task%20shouldn't%20reflect%20complete%20until%20all%20of%20the%20corresponding%20subtasks%20are%20complete.%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EIs%20there%20a%20setting%20I%20can%20use%20that%20will%20fix%20this%3F%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%3CSPAN%20class%3D%22lia-inline-image-display-wrapper%20lia-image-align-inline%22%20style%3D%22width%3A%20936px%3B%22%3E%3CIMG%20src%3D%22https%3A%2F%2Fgxcuf89792.i.lithium.com%2Ft5%2Fimage%2Fserverpage%2Fimage-id%2F130391iB7944A39007F9FCE%2Fimage-size%2Flarge%3Fv%3D1.0%26amp%3Bpx%3D999%22%20alt%3D%22MS%20Project-summary%20task%20issue%20image.PNG%22%20title%3D%22MS%20Project-summary%20task%20issue%20image.PNG%22%20%2F%3E%3C%2FSPAN%3E%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-LABS%20id%3D%22lingo-labs-839971%22%20slang%3D%22en-US%22%3E%3CLINGO-LABEL%3EProject%3C%2FLINGO-LABEL%3E%3C%2FLINGO-LABS%3E%3CLINGO-SUB%20id%3D%22lingo-sub-840271%22%20slang%3D%22en-US%22%3ERe%3A%20Summary%20task%20doesn't%20consider%20sub%20task%20dates%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-840271%22%20slang%3D%22en-US%22%3E%3CP%3EHello%26nbsp%3B%3CA%20href%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fuser%2Fviewprofilepage%2Fuser-id%2F272245%22%20target%3D%22_blank%22%3E%40Kateraid%3C%2FA%3E%26nbsp%3B%3C%2FP%3E%0A%3CP%3EThis%20is%20because%20your%20tasks%20are%20manually%20scheduled%20in%20your%20example%20and%20those%20tasks%20do%20not%20have%20any%20duration.%20Either%20add%20duration%20to%20the%20manually%20scheduled%20tasks%20or%20switch%20to%20auto%20scheduled%20tasks%20like%20in%20the%20example%20below%3A%3C%2FP%3E%0A%3CP%3E%26nbsp%3B%3C%2FP%3E%0A%3CP%3E%3CSPAN%20class%3D%22lia-inline-image-display-wrapper%20lia-image-align-center%22%20style%3D%22width%3A%20400px%3B%22%3E%3CIMG%20src%3D%22https%3A%2F%2Fgxcuf89792.i.lithium.com%2Ft5%2Fimage%2Fserverpage%2Fimage-id%2F130409i1118F7F07B429C87%2Fimage-size%2Fmedium%3Fv%3D1.0%26amp%3Bpx%3D400%22%20alt%3D%22manualvsAuto.png%22%20title%3D%22manualvsAuto.png%22%20%2F%3E%3C%2FSPAN%3E%3C%2FP%3E%0A%3CP%3E%26nbsp%3BHope%20that%20helps%3C%2FP%3E%0A%3CP%3EPaul%3C%2FP%3E%0A%3CP%3E%26nbsp%3B%3C%2FP%3E%3C%2FLINGO-BODY%3E
Highlighted
Contributor

Hi folks - I am new to MS project and am struggling with the metadata on summary tasks. You can see in this image I have an 'Initiate Project' summary task which consists of several sub-tasks. When I mark one of the subtasks complete, Project marks the summary task complete too. Even though all of the other subtasks are still incomplete. The summary task shouldn't reflect complete until all of the corresponding subtasks are complete. 

 

Is there a setting I can use that will fix this? 

 

MS Project-summary task issue image.PNG

1 Reply
Highlighted
Solution

Hello @Kateraid 

This is because your tasks are manually scheduled in your example and those tasks do not have any duration. Either add duration to the manually scheduled tasks or switch to auto scheduled tasks like in the example below:

 

manualvsAuto.png

 Hope that helps

Paul

 

Related Conversations
Date filtering of Bing Searches
PhilipE3 in Discussions on
2 Replies
Setting Date in Stored Procedure
Tim Hunter in SQL Server on
1 Replies
Hide tasks from task board when parent item is blocked
gresdawg in Azure on
0 Replies