Aug 10 2023 04:00 AM
How can I specify a quarterly budget for a group of tasks ?
e.g Actual effort for all tasks in a quarter (April 1 - May 30) should not cross 1000 hours.
Thanks
Aug 10 2023 08:35 AM
Aug 10 2023 11:29 PM
Aug 11 2023 10:40 AM
I can only see a couple of options.
The first involves a manual calculation of Budget Work minus Cumulative Work for a 3 month time span. Reset the budget each quarter and run the calculation.
The second option requires VBA to essentially do the calculation and dump the result in a custom field at project level.
I only use the desktop version of Project so perhaps there are more ideas with enterprise versions. Maybe someone else will jump in with their suggestions.
John
Aug 11 2023 11:02 PM
@John-project Thanks John for your reply.
I tried a slightly different approach. In Task Usage, I set the budget for each quarter manually. (I have done this for just 3 quarters for the time being but if the project extends, I will have to set it for subsequent quarters manually too!)
But I achieved what I wanted. I can see the Budget Cost and Cost for each quarter.
I wish though that I could see BalanceBudget (a custom field) = [BudgetCost]-[Cost] too in task usage. Have to figure out how to do that!
Aug 12 2023 08:37 AM
You can use a custom field formula for budget cost minus cost but it will only apply at the Project Summary task level.
Does that not work for you? If not, what exactly do you want?
John
Aug 12 2023 08:56 PM
Aug 13 2023 06:48 AM
SolutionAug 13 2023 08:53 AM
Aug 13 2023 06:48 AM
Solution