Showing project tasks in WBS order in Power BI report

%3CLINGO-SUB%20id%3D%22lingo-sub-3398406%22%20slang%3D%22en-US%22%3EShowing%20project%20tasks%20in%20WBS%20order%20in%20Power%20BI%20report%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3398406%22%20slang%3D%22en-US%22%3E%3CP%3EHi%20Team%3C%2FP%3E%3CP%3EI'm%20using%20the%20Gantt%202.2.3%20Power%20BI%20visual%20to%20show%20tasks%20in%20a%20project.%26nbsp%3B%20The%20problem%20is%20the%20tasks%20are%20in%20alphabetical%20order.%26nbsp%3B%20How%20can%20I%20change%20to%20WBS%20order%3F%3C%2FP%3E%3CP%3EMany%20thanks%26nbsp%3B%3C%2FP%3E%3CP%3EJames%3C%2FP%3E%3C%2FLINGO-BODY%3E
Contributor

Hi Team

I'm using the Gantt 2.2.3 Power BI visual to show tasks in a project.  The problem is the tasks are in alphabetical order.  How can I change to WBS order?

Many thanks 

James

0 Replies