Should the capacity of a enterprise resource change daily?

Iron Contributor

We have Project Server 2019.

Should the capacity of a enterprise resource change daily in reporting database?

If we have -5 month and +36 month project server additional settings, the first record in [WSS_PWA].[pjrep].[MSP_EpmResourceByDay] be resource creation date minus 5 month and the last record be current date plus 36 month.

With best regards, Vasily.

1 Reply
best response confirmed by Vasily_Zaytsev (Iron Contributor)
Solution

Hi @Vasily_Zaytsev ,

This will update daily, there is a job that runs each night to keep this data updated:

PaulMather_0-1634826383455.png

Paul