Feb 13 2023 05:38 AM
Hello,
I'm facing an issue with shared resources:
I have 2 project files (A.mpp & B.mpp) using shared resources in C.mpp
I got rid of B.mpp, but shared resources show as taken by B.mpp
I tried to :
- recreate B.mpp
- deconnect B.mpp from C.mpp
That only works temporarily. Resources reappear as taken by B.mpp :(
My version MSP is Client de bureau Microsoft® Project® Online MSO (Version 2301 Build 16.0.16026.20002) 64 bits, on a Windows 10 PC Computer
Hope you can help
Thanks
Mark
Feb 13 2023 06:43 AM
@MarkDury --
Open the shared resource pool file Read/Write. Click Resource > Resource Pool > Share Resources. You should see a dialog that looks similar to the one below. Select Project B in this dialog and then click the Break Link button. Close the dialog and save the shared resource pool file. Hope this helps.
Feb 13 2023 08:03 AM