Jul 18 2022 07:52 AM
Hi,
Is there an option to configure MS Project so that it will automatically set a dependency between tasks that are assigned to a given resource?
We want to avoid the need to manually search the resource's last task and then manually set a dependency between that task and the next one.
Sample:
Resource Danny has a tasks that is scheduled to be finished on July 20th.
We want that Danny's next task will automatically begin on July 21st and not on the project's start date.
Is that possible?
Thanks,
Jul 18 2022 09:14 AM
Jul 19 2022 01:09 PM
Jul 23 2022 02:28 AM
@John-project Thank you
Jul 23 2022 06:16 AM