I work with several roadmaps and connect them to different projects.
But i get one Flow created on my account on each roadmap row i add.
It is getting out of hand with way to many flows so i cant view my regular flows anymore.
How to manage these roadmap-flows that are created. Why do they need to be placed on my account together with all the other flows?
Jan 26 2022 10:16 AM
Hello @oskarkuus ,
Unfortunately that is by design. The flows are created in the users account who connects that roadmap row with the project.
Paul