SOLVED

Resources remaining availability in percentages

Copper Contributor

Hello,

I`m trying to generate a MS Project Work Overview report, and in the Remaining availability Graphic on the Hours Scale I need in Percentages %, not in number of hours. (left side)

Can anyone help with a suggestion?

Catalin_MS_0-1686044764136.png

 

 

Thanks,

1 Reply
best response confirmed by Dale Howard (MVP)
Solution
Based on my experience you cannot modify any of the Capacity Planning views, which is unfortunate. I created a set of custom power bi reports which allow me to display the data as needed.