Sep 26 2024 10:20 PM
Good morning,
Pls assist .. I have a 2 calenders on this project. 1. Fabrication 2. Installation. (I've allocated it accordingly to my tasks.)
For this project (SAPPI) my Resources for :
1.'Fabrication' will only be available from 01/10/2024 - 03/11/2024
2. 'Installation will only be available from 04/11/2024 - 09/11/2024.
When I change the resource availability as such and when adding my 'available from' & available to' columns in the Resource sheet, it does not come up as such as well as the max shows 0% and not 100% or 200%. Why , what am i doing wrong? @
Sep 26 2024 11:09 PM
Sep 27 2024 11:15 AM
SolutionHi Jeanine.
The maximum capacity shown in the resource sheet refers to the current day, so if that day is outside the resource's availability range, it will show 0%.
You can check the maximum capacity on any day of the resource's availability range by entering a date within the range in Project > Properties > Project Information > Current Date.
I hope I have helped you.
Ignacio Martin
Sep 27 2024 11:25 AM
Jeanine, in order to help you with your second question, it would be desirable for you to show a screenshot of the tasks table with the tasks to which you refer with their data.
Regards
Ignacio Martin
Sep 27 2024 11:15 AM
SolutionHi Jeanine.
The maximum capacity shown in the resource sheet refers to the current day, so if that day is outside the resource's availability range, it will show 0%.
You can check the maximum capacity on any day of the resource's availability range by entering a date within the range in Project > Properties > Project Information > Current Date.
I hope I have helped you.
Ignacio Martin