Jan 18 2024 02:09 PM - edited Jan 18 2024 02:09 PM
Hello Comrades,
I was hoping that one of you may be able to help me clarify what value a field is displaying in the Project Online (PWA) Project Center. The field in question is the "Finish" field, shown below.
Originally, we were assuming that this was the "Finish date" of the project set in the Project Information, in the Project desktop app.
However, that does not appear to be true. As we have started to run into cases where projects are published and the "Finish date" in the Project Information section does not match the "Finish" value in Project Center.
It seems as though Project Center is either showing the "ProjectLateFinish" date of the project OR the "Finish" of the top-level task in the project? I have been unable to find any documentation on what value is showing in Project Center.
Thanks!
Chris
Jan 19 2024 06:30 AM
Jan 19 2024 10:57 AM - edited Jan 19 2024 11:04 AM
Okay awesome! Thank you. So, what I was calling the "Top-Level" task would be the Project Summary Task.
Would the following be true then?
Project Summary Task Start = ProjectLateStart
Project Summary Task Finish = ProjectLateFinish
Thanks again!
Jan 19 2024 01:28 PM
SolutionJan 19 2024 01:28 PM
Solution