PWA Timesheet Rejected Notification

Copper Contributor

Is there a way to set up PWA to send out email notifications to users when a PM rejects their timesheet?

1 Reply
best response confirmed by wyalib (Copper Contributor)
Solution

Hello @wyalib ,

The PWA notifications are around Tasks, Status Reports and queue job failures as you have probably seen. The options can be seen here: {pwaUrl}/_layouts/15/pwa/Notification/Self_Notification.aspx. Unfortunately timesheets are not included.

Paul