Apr 26 2021 02:34 PM
We have a PWA installation where the project template was configured in such a way that the deliverables list was not created with the project site. We have now changed the template to create this list for all new projects, but are wondering if it is possible to create (even manually) the deliverables list for existing projects. Currently, attempting to view the deliverables of an existing project produces an error indicated the deliverables SharePoint list is not found.
Thanks for any input.
Brent.
Apr 27 2021 01:19 AM
SolutionHello @dBrent,
On a test Project site that doesn't contain the Deliverables list do the following:
Access a Test Project Site > Settings cog > Site Settings > Manage Site Features > Project Web App Connectivity Feature > Click Deactivate > Click Deactivate this feature > Project Web App Connectivity Feature > Click Activate
By deactivating then activating the feature, that should create the Deliverables list if it doesn't exist on that Project site. Fully test the test Project site to ensure you are happy this all works as expected with the Deliverables, Risks and Issues then repeat on other sites.
Paul
Apr 27 2021 07:27 AM
Apr 27 2021 01:19 AM
SolutionHello @dBrent,
On a test Project site that doesn't contain the Deliverables list do the following:
Access a Test Project Site > Settings cog > Site Settings > Manage Site Features > Project Web App Connectivity Feature > Click Deactivate > Click Deactivate this feature > Project Web App Connectivity Feature > Click Activate
By deactivating then activating the feature, that should create the Deliverables list if it doesn't exist on that Project site. Fully test the test Project site to ensure you are happy this all works as expected with the Deliverables, Risks and Issues then repeat on other sites.
Paul