Pulling Azure DevOps Epic into Project Online

Copper Contributor

Is it possible pull an Epic and all of it's associated Features, User Stories and Tasks into Project Online? I see that you can do it on a line by line basis, but it is very onerous if it is a big Epic.

Thank you.

2 Replies

Hello @ShelaghLennon ,

There is nothing out of the box from Microsoft for Project Online and Azure DevOps integration but it is possible to build something yourself either in code or even using Power Automate - here is a simple example using Power Automate: https://pwmather.wordpress.com/2019/09/07/projectonline-and-azuredevops-integration-using-microsoftf...

Alternatively you could look for 3rd part add-ons 

Paul

Hi@Paul Mather ,

 

Thank you for your response. I did come across your post about this. Unfortunately Power Automate is not something that I have used, and I don't have a coding background, but I am trying to muddle my way through in the hope that I can replicate what you have done.

Many thanks.

Shelagh