Project Web App Resource Replacement

Copper Contributor

We are using MS Office 365. We had setup PWA (Project Web App). Initially we had added PWA resources (local) and assigned them to tasks. Some projects have made progress. Now I am replacing the local PWA resources with Azure Users (Same person in real). I am getting an alert that only the remaining work will be replaced however the already progress work will not be replaced or assigned to Azure user. How can I resolve this issue. I don’t want to keep 2 accounts for a same person 1 is PWA resource and 1 is Azure User. Please advise. I want to completely replace a PWA local resource with Azure user without. Goal is to keep only the azure user account and delete the existing local PWA resource. Please advise.

0 Replies