SOLVED

Project tasks assigned to resource are listed under Tasks, but not listed in Timesheet

Copper Contributor

Hi,

I have created a project, tasks and assigned it to resources. I have ensured that Tasks are published, not locked and Resources are committed. Tasks are listed under the Tasks of the resource. But same tasks are not listed in the timesheet.

I have deleted the Timesheet in Manage Timesheets and Time Reporting Periods and recreated. Even then no luck.

I am able to add task to timesheet using Add Row -> Select From Existing Assignments. But, assigned tasks should automatically listed under the Timesheet.  Screenshots are pasted for immediate reference.

Thanks & regards

Lingaraju

2 Replies
best response confirmed by Dale Howard (MVP)
Solution

Hello @Lingaraju_CH ,

Are the Timesheets set to be prepopulated with the current task assignments?

PaulMather_0-1637335468726.png

 

Setting here: {pwaUrl}/_layouts/15/pwa/Admin/TSSettings.aspx

Paul

Dear @Paul Mather 

Thank you for the reply. Issue is resolved. Customize Timesheet Link helped me.