Nov 19 2021 04:03 AM
I have created a project, tasks and assigned it to resources. I have ensured that Tasks are published, not locked and Resources are committed. Tasks are listed under the Tasks of the resource. But same tasks are not listed in the timesheet.
I have deleted the Timesheet in Manage Timesheets and Time Reporting Periods and recreated. Even then no luck.
I am able to add task to timesheet using Add Row -> Select From Existing Assignments. But, assigned tasks should automatically listed under the Timesheet. Screenshots are pasted for immediate reference.
Thanks & regards
Lingaraju
Nov 19 2021 07:25 AM
SolutionHello @Lingaraju_CH ,
Are the Timesheets set to be prepopulated with the current task assignments?
Setting here: {pwaUrl}/_layouts/15/pwa/Admin/TSSettings.aspx
Paul
Nov 25 2021 09:55 PM
Nov 19 2021 07:25 AM
SolutionHello @Lingaraju_CH ,
Are the Timesheets set to be prepopulated with the current task assignments?
Setting here: {pwaUrl}/_layouts/15/pwa/Admin/TSSettings.aspx
Paul