Feb 02 2021 05:53 AM
Hi
I get the attached error when trying to build a site from a template. This happens for all the templates in our library, new and old.
Feb 02 2021 10:57 AM
Hello @pauleast ,
What happens when the EPT is set to use the default "Project Site" template - does that work?
Paul
Feb 03 2021 03:59 AM
@Paul Mather we don't have a default one as in OOB from Microsoft as we have a custom build. What does seem to be happening is the failure of the site build doesn't happen when we create a project from 'new' whereas using our pipeline list does...this links list items to custom fields in the project details.
Feb 03 2021 08:53 AM
Hi @pauleast ,
As a test, can you set one EPT to use the OOB Project Site template and create a Project from the pipeline list to see if it repros there?
Paul
Feb 05 2021 07:34 AM
Feb 05 2021 07:37 AM
Hello @pauleast ,
On the EPT in the Site Template option in Project Online, there will be "Project Site" - that is the OOB project site template.
Paul
Feb 08 2021 01:49 AM
@Paul Mather thanks, found it! Unfortunately no luck, it fails to build a site with the default template.