Project PWA Change or Restart Workflow and Skip to Workflow Stage

Copper Contributor

In PWA when I go to the change or restart workflow and skip to workflow stage option in server settings, and change the project type, the project does not reflect the project site of the new project type that it has been moved to.  

 

What am I not doing, I thought the project would now have the project site that is tied to the project type it was changed to.

2 Replies
I meant that the project does not reflect the project type project site template.
Hi nmanus,
I also faced the same issue. When ever u change the Project type in pwa settings, project will change based on EPT. When comes to project site it won't. So, what u have to do is go to pwa settings>connected sharepoint site>delete that project site there. Then open the project republish your project. Project site will automatically created, based on ur ept settings(automatically create a site on next publish). Suggestion is try to create a test project.