SOLVED

Project progress not updating after approving timesheet

Brass Contributor

Hi guys

 

I am trying to get project progress on individual tasks to update (%complete) after approving timesheets submitted by my team. Unfortunately the progress is not moving, it's still 0% for example if a task is complete and approval given.

 

Please assist if possible.

 

 

4 Replies

Hello @khyron,

Are you using single entry mode? On the PWA Settings page, check "Timesheet Settings and Default" settings, scroll to the bottom of the page and look for "Single Entry Mode". This means that the timesheet data will also create a Task Status update. Once this Task Status update is approved by the Task Status Manage into the project plan it will progress the task. More details around timesheets can be seen here: https://docs.microsoft.com/en-us/projectonline/set-up-timesheets 

Paul

Thanks that did the trick @Paul Mather 

best response confirmed by khyron (Brass Contributor)
Solution

Thanks @khyron - are you able to mark the reply as the answer / best response so this will help others too?

Paul

Yes - sorry , I'm new here.

 

I think I clicked on the wrong reply as the best response

1 best response

Accepted Solutions
best response confirmed by khyron (Brass Contributor)
Solution

Thanks @khyron - are you able to mark the reply as the answer / best response so this will help others too?

Paul

View solution in original post