Oct 04 2022 08:45 PM
Good day
Recently I've noticed that our PWA projects are not considering task assignments on other projects, so we can now only level a resource only for one project. This used to happen automatically I don't know if Microsoft changed something or we changed some setting to disable the connection.
Please assist! because now we find that recourses are always over allocated
Regards
Mpafane
Oct 05 2022 12:46 AM
SolutionHello @Mpafane ,
Are you looking at the projects in MS Project? If so, do you have this option enabled when login in to the PWA account from MS Project?
Paul
Oct 05 2022 01:57 AM
@Paul_Mather Thank you so much that's what was wrong it now works
Oct 05 2022 12:46 AM
SolutionHello @Mpafane ,
Are you looking at the projects in MS Project? If so, do you have this option enabled when login in to the PWA account from MS Project?
Paul