SOLVED

Project planner not synchronizing tasks on other PWA projects

Copper Contributor

Good day 

 

Recently I've noticed that our PWA projects are not considering task assignments on other projects, so we can now only level a resource only for one project. This used to happen automatically I don't know if Microsoft changed something or we changed some setting to disable the connection.

 

Please assist! because now we find that recourses are always over allocated 

 

Regards 

Mpafane

2 Replies
best response confirmed by Mpafane (Copper Contributor)
Solution

Hello @Mpafane ,

Are you looking at the projects in MS Project? If so, do you have this option enabled when login in to the PWA account from MS Project?

PaulMather_0-1664955937583.png

 

Paul

@Paul Mather  Thank you so much that's what was wrong it now works

1 best response

Accepted Solutions
best response confirmed by Mpafane (Copper Contributor)
Solution

Hello @Mpafane ,

Are you looking at the projects in MS Project? If so, do you have this option enabled when login in to the PWA account from MS Project?

PaulMather_0-1664955937583.png

 

Paul

View solution in original post