Project Online %work and actual cost ERROR

%3CLINGO-SUB%20id%3D%22lingo-sub-873638%22%20slang%3D%22en-US%22%3EProject%20Online%20%25work%20and%20actual%20cost%20ERROR%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-873638%22%20slang%3D%22en-US%22%3E%3CP%3EHi%20All%2C%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EI%20start%20pulling%20out%20my%20hairs!%3C%2FP%3E%3CP%3EWhen%20manipulating%20a%20schedule%20with%20Project%20Online%2C%20it%20happens%20quite%20often%20that%20the%20%25work%20starts%20not%20working%20at%20all.%20The%20summary%20tasks%20don't%20populate%20the%20%25works%20done%20anymore%20(stays%20at%200%25)%20and%20the%20actual%20cost%20doesn't%20match%20the%20value%20entered%20into%20%25work%20done.%20If%20I%20click%20on%20the%20menu%20buttons%20(0%2C%2025%2C%2050%2C%2075%20or%20100%25)%2C%20the%20actual%20cost%20is%20right%2C%20but%20the%20%25work%20goes%20back%20to%200...just%20craziness.%3C%2FP%3E%3CP%3EAnyone%20has%20already%20experienced%20that%20%3F%20only%20me%20and%20my%20colleagues%20%3F%3C%2FP%3E%3CDIV%20class%3D%22mceNonEditable%20lia-copypaste-placeholder%22%3E%26nbsp%3B%3C%2FDIV%3E%3CP%3EThanks%20for%20your%20help%2C%3C%2FP%3E%3CP%3ECheers%3C%2FP%3E%3CP%3EJL%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-LABS%20id%3D%22lingo-labs-873638%22%20slang%3D%22en-US%22%3E%3CLINGO-LABEL%3EOnline%3C%2FLINGO-LABEL%3E%3CLINGO-LABEL%3EProject%3C%2FLINGO-LABEL%3E%3C%2FLINGO-LABS%3E%3CLINGO-SUB%20id%3D%22lingo-sub-873694%22%20slang%3D%22en-US%22%3ERe%3A%20Project%20Online%20%25work%20and%20actual%20cost%20ERROR%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-873694%22%20slang%3D%22en-US%22%3E%3CP%3ECan%20you%20check%20the%20%5BWork%5D%20value%20for%20tasks%3F%3CA%20href%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fuser%2Fviewprofilepage%2Fuser-id%2F406892%22%20target%3D%22_blank%22%3E%40JeanLouis%3C%2FA%3E%3C%2FP%3E%3CP%3ESimply%20right%20click%20on%20one%20of%20the%20columns%20and%20%22insert%20Column%22%20%3D%26gt%3B%20%5BWork%5D%3C%2FP%3E%3CP%3Efor%20the%20%25work%20roll-up%20value%20you%20should%20have%20work%20assigned%20to%20each%20task.%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-875491%22%20slang%3D%22en-US%22%3ERe%3A%20Project%20Online%20%25work%20and%20actual%20cost%20ERROR%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-875491%22%20slang%3D%22en-US%22%3E%3CP%3EHi%2C%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EAs%20you%20were%20asking%20the%20question%2C%20I%20thought%20trying%20other%20columns%20as%20well.%3C%2FP%3E%3CP%3EThe%20%5Bwork%7D%20value%20remains%20at%200%2C%20but%20if%26nbsp%3B%20I%20use%20th%20%5B%25%20complete%5D%20column%20instead%20of%20the%20%5B%25%20work%20complete%5D%2C%20it%20works%20!%3C%2FP%3E%3CP%3EWhat%20is%20the%20difference%20between%20the%202%20columns%20%3F%3F%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EThanks%20a%20lot%3C%2FP%3E%3CP%3EJL%3C%2FP%3E%3C%2FLINGO-BODY%3E
New Contributor

Hi All,

 

I start pulling out my hairs!

When manipulating a schedule with Project Online, it happens quite often that the %work starts not working at all. The summary tasks don't populate the %works done anymore (stays at 0%) and the actual cost doesn't match the value entered into %work done. If I click on the menu buttons (0, 25, 50, 75 or 100%), the actual cost is right, but the %work goes back to 0...just craziness.

Anyone has already experienced that ? only me and my colleagues ?

 

Thanks for your help,

Cheers

JL

 

 

2 Replies

Can you check the [Work] value for tasks?@JeanLouis

Simply right click on one of the columns and "insert Column" => [Work]

for the %work roll-up value you should have work assigned to each task.

 

 

best response confirmed by JeanLouis (New Contributor)
Solution

Hi,

 

As you were asking the question, I thought trying other columns as well.

The [work} value remains at 0, but if  I use th [% complete] column instead of the [% work complete], it works !

What is the difference between the 2 columns ??

 

Thanks a lot

JL