Sep 24 2019 08:49 PM
Hi All,
I start pulling out my hairs!
When manipulating a schedule with Project Online, it happens quite often that the %work starts not working at all. The summary tasks don't populate the %works done anymore (stays at 0%) and the actual cost doesn't match the value entered into %work done. If I click on the menu buttons (0, 25, 50, 75 or 100%), the actual cost is right, but the %work goes back to 0...just craziness.
Anyone has already experienced that ? only me and my colleagues ?
Thanks for your help,
Cheers
JL
Sep 24 2019 10:02 PM
Can you check the [Work] value for tasks?@JeanLouis
Simply right click on one of the columns and "insert Column" => [Work]
for the %work roll-up value you should have work assigned to each task.
Sep 25 2019 01:11 PM
SolutionHi,
As you were asking the question, I thought trying other columns as well.
The [work} value remains at 0, but if I use th [% complete] column instead of the [% work complete], it works !
What is the difference between the 2 columns ??
Thanks a lot
JL
Sep 25 2019 01:11 PM
SolutionHi,
As you were asking the question, I thought trying other columns as well.
The [work} value remains at 0, but if I use th [% complete] column instead of the [% work complete], it works !
What is the difference between the 2 columns ??
Thanks a lot
JL